
Project Overview
Dismantling, Shifting, Erection, Wiring, Testing & Commissioning of Electrical Equipments along with Control / Relay Panels etc. for Extension / Addition of 01 No. 600 MVA, 500 / 220 kV Auto Transformer Bay & 01 No. 250 MVA Auto Transformer at 500 kV Grid Station Nokhar.
AHTE has completed above scope of within timelines and delivered the project.
Scope of Work
Dismantling, Shifting, Erection, Wiring, Testing & Commissioning
Challenges
The extension work at the 500 kV Grid Station Nokhar was a highly technical and challenging task. The biggest challenge we faced was acquiring shutdowns and working safely within the existing energized grid station