Project Overview
SHIFTING, LOADING, UNLOADING OF 160MVA, 220/132KV AUTO TRANSFORMER (MAKE JIANGSU HUAPENG) FROM 500KV GRID STATION MULTAN TO 220KV TSG MODEL GRID STATION NKLP LAHORE ALONG WITH ERECTION, INSTALLATION, TESTING & COMMISSIONING WORKS OF 160MVA 220/132KV AUTO TRANSFORMER AT 220KV TSG MODEL GRID STATION NKLP LAHORE AND OTHER MISCELLANEOUS WORKS
AHTE has completed above scope of within timelines and delivered the project.
Scope of Work
SHIFTING, ERECTION and INSTALLATION of 220/132KV AUTO TRANSFORMER
Challenges
SHIFTING, ERECTION and INSTALLATION of 220/132KV Auto Transformer is very technical and challenging job for any contractor. One of the biggest challenges we faced is the maneuvering space for the transformer into existing Model Grid while making sure the Safety of existing roads, buildings and equipment.
Our specialised team put extra efforts in Safely INSTALLATION of new transformer and Dismantling of Old Transformer.